15. At the end of any intervention in wetlands and bodies of water,
(1)  any temporary undertaking must be dismantled, subject to any contrary provision;
(2)  the banks must be stable and protected against erosion, preferably by means of the technique most conducive to maintaining the natural character of the area;
(3)  except for sylvicultural treatments, the areas concerned must be restored within one year following the end of the intervention including, where applicable,
(a)  land restoration;
(b)  in the unwatered zone, revegetation of the areas concerned if they have been stripped of vegetation or soil, except
i.  for drilling work;
ii.  for taking samples, conducting surveys, making technical surveys, carrying out archaeological excavations and taking measurements, in respect of the tree stratum;
iii.  where the revegetation jeopardizes the stability or security of an undertaking, in respect of the tree and shrub stratum.
O.C. 871-2020, s. 15; O.C. 1461-2022, s. 6.
15. At the end of any intervention in wetlands and bodies of water,
(1)  any temporary undertaking must be dismantled, subject to any contrary provision;
(2)  the banks must be stable and protected against erosion, preferably by means of the technique most conducive to maintaining the natural character of the area;
(3)  except for sylvicultural treatments, the areas concerned must be restored within one year following the end of the intervention including, where applicable,
(a)  land restoration;
(b)  in the unwatered zone, revegetation of the areas concerned if they have been stripped of vegetation or soil, except
i.  for drilling work;
ii.  for preliminary survey work, in respect of the tree stratum;
iii.  where the revegetation jeopardizes the stability or security of an undertaking, in respect of the tree and shrub stratum.
O.C. 871-2020, s. 15.
In force: 2020-12-31
15. At the end of any intervention in wetlands and bodies of water,
(1)  any temporary undertaking must be dismantled, subject to any contrary provision;
(2)  the banks must be stable and protected against erosion, preferably by means of the technique most conducive to maintaining the natural character of the area;
(3)  except for sylvicultural treatments, the areas concerned must be restored within one year following the end of the intervention including, where applicable,
(a)  land restoration;
(b)  in the unwatered zone, revegetation of the areas concerned if they have been stripped of vegetation or soil, except
i.  for drilling work;
ii.  for preliminary survey work, in respect of the tree stratum;
iii.  where the revegetation jeopardizes the stability or security of an undertaking, in respect of the tree and shrub stratum.